Pile Construction [EX1-SIG]
After clicking on ‘Construction> Substructure Construction> Pile Construction' in the navigation treeview, follow the steps to define the Pile Construction. You can use the collapsed documentation page below for more information on the explanations of each parameter.
1 | Click three-dots icon on Stage cell and select a Construction Stage as SubstrConstStage. | |
2 | Click three-dots on the cell of the All Piles under Substructure and pick all the foundations. |
|
3 | Keep the Individual Piles and Self Weight Factor as default. |
|
4 | Proceed to the next step to verify the model. |
The completed pile construction is illustrated below. Please verify that you have the same model on your end by examining each view provided here. For more information on how to perform visual checks, refer to the quick tips.