Please follow the instructions provided below to define construction of superstructure bridge components.
1 | Navigate to Loading > Construction > Superstructre > Superstructure Attachment Construction | |
2 | Click three-dots icon on Stage cell and click select. | |
3 | Select "BarrierConst" as stage. |
|
4 | Click three-dots icon on Superstructure Attachment Elements cell and click pick.
|
|
5 | In the project, a total of 3 spans and 6 barriers were defined. Now, pick all the defined barriers from 3D view. |
|
1 | Navigate to Superstructure Attachment Construction under Superstructure Construction on the tree view. |
2 | Copy General from model inputs and paste into OpenBrIM. |
Superstructure Attachment Construction |
---|
General |
Barrier_Const BarrierConst [Barrier1,Barrier2,Barrier3,CustBar3,CustBar2,CustBar1] 1.0000 YES |
, multiple selections available,
Related content
Girder Construction [EX1-PIG]
Girder Construction [EX1-PIG]
More like this
Construction Stage [EX1-PIG]
Construction Stage [EX1-PIG]
More like this
Bearing Construction [EX1-PIG]
Bearing Construction [EX1-PIG]
More like this
Deck Construction [EX1-PIG]
Deck Construction [EX1-PIG]
Read with this
Superstructure Attachment Construction [EX1-SIG]
Superstructure Attachment Construction [EX1-SIG]
More like this
Custom Diaphragm [EX1-PIG]
Custom Diaphragm [EX1-PIG]
Read with this