Sections [EX1-STG]
This part is to inform about the general purposes of section definitions.
Please follow the instructions provided below to set section definitions to be used in this bridge example.
1 | Navigate to Properties > Sections |
|
2 | To import a section, click on the three-dot icon located on the first cell of the Name and select "Import Section". | |
3 | Select OpenBrIM Bridge Objects > Basic Sections > Basic Shapes > Rectangle |
|
4 | Enter Width as 60 and Depth as 84 in import section editor. | |
5 | Click Import | |
6 | Rename this section as HammerHeadSec | |
7 | Assign Material as Fc_4ksi (If the material Fc_4ksi is already assigned by default, there is no need to assign it again) | |
8 | Repeat the same steps from 2 to 7 for the second rectangular section Enter Width and Depth
Rename this section as HalfHammerHeadSec1 Assign Material as Fc_4ksi |
|
9 | Repeat the same steps from 2 to 7 for the third rectangular section Enter Witdh and Depth
Rename this section as HalfHammerHeadSec2 Assign Material as: Fc_4ksi |
|
10 | Repeat the same steps from 2 to 7 for the third rectangular section Enter Witdh and Depth
Rename this section as ColSec_P2 Assign Material as: Fc_5ksi |
|
11 | Repeat the same steps from 2 to 7 for the third rectangular section Enter Witdh and Depth
Rename this section as ColSec_P3 Assign Material as: Fc_5ksi |
|
12 | Repeat the same steps from 2 to 7 for the third rectangular section Enter Witdh and Depth
Rename this section as PileSec Assign Material as: Fc_5ksi |
|
13 | Import another section by selecting
Assign Material as: A709_50W | |
14 | Import another section by selecting
OpenBrIM Bridge Objects > AISC Steel Shape Database > L Type > AISCWT6X6X7/8 Assign Material as: A709_50W | |
15 | Create a new section by defining its name as RigidSection |
|
16 | Copy and paste the data below. RigidSection RigidMaterial 6400.0000 6400.0000 6400.0000 3413333.3333 3413333.3333 3413333.3333 0.0000 YES NO NO |
Completed Sections definitions are illustrated below.
Properties >
Please follow the instructions provided below to set rebar detailing for HammerHeadSec.
1 | From any cell of the HammerHeadSec row, click on three-dots icon to open Section Editor panel. | |
2 | Click + icon at the left top side of the screen. And Select Rebar | |
3 | Enter:
Click Add. |
|
4 | Click again + icon at the left top side of the screen. |
|
5 | The reinforcement identification process will be carried out three times on the bottom reference edge. Select Rebar
Click Add.
| |
6 | Repeat the same step for
values. | |
7 | Click again + icon at the left top side of the screen. |
|
8 | Select Rebar
Click Add. | |
9 | Click … icon shown on left middle edge of rebar. Click Points Spreadsheet. Copy the data below. 0.0000 6.0000
-24.3650 -24.0000
-24.3650 24.0000 |
|
10 | Paste copied data. | |
11 | Click again + icon at the left top side of the screen. |
|
12 | Select Rebar
Click Add. | |
13 | Click … icon shown on right middle edge of rebar. Click Points Spreadsheet. Copy the data below. 0.0000 6.0000
24.3650 -24.0000
24.3650 24.0000 | |
14 | Paste copied data. |
1 | From any cell of the HalfHammerHeadSec1 row, click on three-dots icon to open Section Editor panel. | |
2 | Click + icon at the left top side of the screen. And Select Rebar | |
3 | The reinforcement identification process will be carried out three times on the top reference edge. Enter:
Click Add. |
|
4 | Repeat the same step for
values. | |
5 | Click again + icon at the left top side of the screen. |
|
6 | Select Rebar
Click Add.
| |
7 | Click again + icon at the left top side of the screen. |
|
8 | Select Rebar
Click Add. | |
9 | Click … icon shown on left middle edge of rebar. Click Points Spreadsheet. Copy the data below. |
|
10 | Paste copied data. | |
11 | Click again + icon at the left top side of the screen. |
|
12 | Select Rebar
Click Add. | |
13 | Click … icon shown on right middle edge of rebar. Click Points Spreadsheet. Copy the data below. |
|
14 | Paste copied data. |
1 | From any cell of the HalfHammerHeadSec2 row, click on three-dots icon to open Section Editor panel. | |
2 | Click + icon at the left top side of the screen. And Select Rebar | |
3 | The reinforcement identification process will be carried out three times on the top reference edge. Enter:
Click Add. |
|
4 | Repeat the same step for
values. | |
5 | Click again + icon at the left top side of the screen. |
|
6 | Select Rebar
Click Add.
| |
7 | Click again + icon at the left top side of the screen. |
|
8 | Select Rebar
Click Add. | |
9 | Click … icon shown on left middle edge of rebar. Click Points Spreadsheet. Copy the data below. |
|
10 | Paste copied data. | |
11 | Click again + icon at the left top side of the screen. |
|
12 | Select Rebar
Click Add. | |
13 | Click … icon shown on right middle edge of rebar. Click Points Spreadsheet. Copy the data below. |
|
14 | Paste copied data. |
1 | From any cell of the ColSec_P2 row, click on three-dots icon to open Section Editor panel. |
|
2 | Click + icon at the left top side of the screen. And Select Rebar | |
3 | Enter:
Click Add. |
|
4 | Click again + icon at the left top side of the screen. |
|
5 | Select Rebar
Click Add.
| |
6 | Click again + icon at the left top side of the screen. |
|
7 | Select Rebar
Click Add. | |
8 | Click again + icon at the left top side of the screen. |
|
9 | Select Rebar
Click Add. |
1 | From any cell of the ColSec_P3 row, click on three-dots icon to open Section Editor panel. | |
2 | Click + icon at the left top side of the screen. And Select Rebar | |
3 | Enter:
Click Add. |
|
4 | Click again + icon at the left top side of the screen. |
|
5 | Select Rebar
Click Add.
| |
6 | Click again + icon at the left top side of the screen. |
|
7 | Select Rebar
Click Add. | |
8 | Click again + icon at the left top side of the screen. |
|
9 | Select Rebar