Follow the next steps to define construction of substructure bridge components.

1

Proceed with Pile.

2

Select a Stage as SubstrConstStage.

3

Pick Substructures Above.

4

Click on all the foundations.

5

Click Done.

6

Set Individual Piles as Empty.

7

Set Self Weight Factor to 1.


Follow the below steps to copy and paste all inputs from our data set.

1

Go to Pile under Substructure on the tree view.

2

Copy Pile Construction from model inputs and paste into OpenBrIM.


 Quick Tip: Copy inputs to OpenBrIM

Copy the desired data with the automatic copy button in the upper left corner.

Click on the first cell in and use the Ctrl+V shortcut to paste.

If icon won’t appear, collapse page tree menu by clicking on arrow or using shortcut “[”.

While pasting large data, it would be handy to turn of Auto-refresh .

Pile

Pile Construction

PC1	SubstrConstStage	[Footing1,Footing2]	[]	1