Follow the next steps to define construction of substructure bridge components.
1 | Go to Construction/Substructure Construction, click Bearing. | |
2 | Select a Stage at Superstructure Connection Construction tab as GirderStage. | |
3 | Pick Insertion Points. | |
4 | Click all the Insertion Points. | |
5 | Click Done. |
Follow the below steps to copy and paste all inputs from our data set.
1 | Go to Bearing under Substructure Construction on the tree view. |
2 | Copy Superstructure Connection Construction from model inputs and paste into OpenBrIM. |
Bearing |
---|
Superstructure Connection Construction SCC1 GirderStage [IP8,IP7,IP6,IP5,IP4,IP3,IP2,IP1,IP12,IP11,IP10,IP9,IP16,IP15,IP14,IP13] |
0 Comments