Follow the next steps to define construction of substructure bridge components.
1 | Proceed with Pile. | |
2 | Select a Stage as SubstrConstStage. | |
3 | Pick Substructures Above. | |
4 | Click on all the foundations. | |
5 | Click Done. | |
6 | Set Individual Piles as Empty. | |
7 | Set Self Weight Factor to 1. |
Follow the below steps to copy and paste all inputs from our data set.
1 | Go to Pile under Substructure on the tree view. |
2 | Copy Pile Construction from model inputs and paste into OpenBrIM. |
Pile |
---|
Pile Construction PC1 SubstrConstStage [Footing1,Footing2] [] 1 |