Please follow the instructions provided below to define construction of superstructure bridge components.
1 | Navigate to Loading > Construction > Superstructre > Superstructure Attachment Construction | |
2 | Click three-dots icon on Stage cell and click select. | |
3 | Select "BridgeConst" as stage. | |
4 | Click three-dots icon on Superstructure Attachment Elements cell and click pick. | |
5 | In the project, a total of 3 spans and 6 barriers were defined. Now, pick all the defined barriers from 3D view. |
Follow the below steps to copy and paste all inputs from our data set.
1 | Navigate to Superstructure Attachment Construction under Superstructure on the tree view. |
2 | Copy General from model inputs and paste into OpenBrIM. |
Superstructure Attachment Construction |
---|
General |
Barrier_Const BridgeConst [Barrier1,Barrier2,Barrier3,CustBar3,CustBar2,CustBar1] 1.0000 YES |
Add Comment