Follow the next steps to define construction of substructure bridge components.
1 | Go to Loading/Construction/Superstructure, click Deck. | |
2 | Deck pouring and hardening are the states of deck construction stage and should be specified here. | |
3 | Go to Deck Casting tab. | |
4 | Specify names of the deck construction stages in Name. | |
5 | Select pouring stages in Pouring Stage (Weight Only) and hardening stages in Hardening Stage (Gains Stiffness). |
Follow the below steps to copy and paste all inputs from our data set.
1 | Go to Deck under Superstructure on the tree view. |
2 | Copy Deck Casting, Longitudinal and Transverse from model inputs and paste into OpenBrIM. |
3 | Go to Girder Erection (Complete) under Superstructure on the tree view. |
4 | Copy Girder Construction from model inputs and paste into OpenBrIM. |
5 | Go to Superstructure Attachment Construction under Superstructure on the tree view. |
6 | Copy General from model inputs and paste into OpenBrIM. |
Bearing |
---|
Superstructure Connection Construction SCC1 GirderStage [IP8,IP7,IP6,IP5,IP4,IP3,IP2,IP1,IP12,IP11,IP10,IP9,IP16,IP15,IP14,IP13] |
Pier Cap/End Bent (Complete) |
---|
Pier Cap Construction PCC1 SubstrConstStage [PierCap1,PierCap2] 1 |
Pier Column |
---|
Pier Column Construction PCC2 SubstrConstStage [PierColumn1,PierColumn2,PierColumn3,PierColumn4,PierColumn5] 1 |
Foundation (Complete) |
---|
Foundation Construction FC1 SubstrConstStage [Footing1,Footing2] 1 |
Pile |
---|
Pile Construction PC1 SubstrConstStage [Footing1,Footing2] [] 1 |