Girder erection is typically only necessary to consider the non-composite state of girders in a design process. As a result, in general industry practice, girders and cross frames are erected in a single stage. However, if the user needs to model a detailed girder erection process, they can utilize the features available under the 'Girder Erection (Partial)' section

Info

Please follow the instructions provided below to define construction of bridge components.

1

Navigate to Loading > Constucture Construction > Superstructre > Deck Erection (Complete)

2

Click three-dots icon on GirderStage cell.

Select the construction stage as 'GirderStage'

3

Click three-dots icon on Bridge cell.

Set the Bridge as 'BRG1'

...