Girder erection is typically only necessary to consider the non-composite state of girders in a design process. As a result, in general industry practice, girders and cross frames are erected in a single stage. However, if the user needs to model a detailed girder erection process, they can utilize the features available under the 'Girder Erection (Partial)' section

Info

Please follow the instructions provided below to define construction of bridge components.

1

Navigate to Loading > Construction > Superstructre > Deck Erection (Complete)

Image Added

Image Added

2

Click three-dots icon on GirderStage cell.

Select the construction stage as 'GirderStage'

3

Click three-dots icon on Bridge cell.

Set the Bridge as 'BRG1'

Image Added

...

Insert excerpt
_ConfluenceInclusions
_ConfluenceInclusions
nameCopyPaste
nopaneltrue

1

Navigate to Girder Erection (Complete) under Superstructure on the tree view.

2

Copy Girder Construction from model inputs and paste into OpenBrIM

...

Insert excerpt
_ConfluenceInclusions
_ConfluenceInclusions
namePasteTip
nopaneltrue

Girder Erecetion (Complete)

Girder Construction

Code Block
languagexml
GCE1	GirderStage	BRG1