Follow the below steps to learn how to verify the staged construction model to ensure an accurate representation of construction sequencing.

1

Open the Model: Open the OpenBrIM APP to either initiate a new project or access a previously created model.

Image Added
2

Set Up Staged Construction:

Navigate to Construction Stage and define each construction stage in the model.

These stages typically encompass different phases such as foundational infrastructure, structural systems, flooring, exterior finishing, and more.

Image Added

3

Identify the previous stage (Prior Stage) of each stage.

Also, create a timeline with the start and end dates for each stage. These dates should correspond to the actual construction order.

Image Added
4Image Added

5

Checking Staged Construction Model: Start an analysis on OpenBrIM

Image Added
6

Checking Staged Construction Model: Click FEM View Settings to select the size of the FE objects and the support/local axis size by moving the slide bar

Image Added
7

For a more comprehensive understanding of Finite Element Analysis (FEA), please visit the following link. Finite Element Model

Step 2: Checking Applied Loads

...