1 | Navigate to Properties > Sections | |||||
2 | To import a section, click on the three-dot icon located on the first cell of the Name and select "Import Section". | |||||
3 | Select OpenBrIM Bridge Objects > Basic Sections > Basic Shapes > Rectangle | |||||
4 | Enter Width as 54 60 and Depth as 69 84 in import section editor. | |||||
5 | Click Import | |||||
6 | Rename this section as HammerHeadSec | |||||
7 | Assign Material as Fc_4ksi (If the material type came as default, there is no need to assign) | |||||
8 | Repeat the same steps from 2 to 7 for the second rectangular section Enter Witdh and Depth
Rename this section as HalfHammerHeadSec1 Assign Material as Fc_4ksi | |||||
9 | Repeat the same steps from 2 to 7 for the third rectangular section Enter Witdh and Depth
Rename this section as HalfHammerHeadSec2 Assign Material as: Fc_4ksi | |||||
10 | Repeat the same steps from 2 to 7 for the third rectangular section Enter Witdh and Depth
Rename this section as ColSec_P2 Assign Material as: Fc_5ksi | |||||
11 | Repeat the same steps from 2 to 7 for the third rectangular section Enter Witdh and Depth
Rename this section as ColSec_P3 Assign Material as: Fc_5ksi | |||||
12 | Repeat the same steps from 2 to 7 for the third rectangular section Enter Witdh and Depth
Rename this section as PileSec Assign Material as: Fc_5ksi | |||||
13 | Import another section by selecting
Assign Material as: A709_50W | |||||
14 | Import another section by selecting OpenBrIM Bridge Objects > AISC Steel Shape Database > L Type > AISCWT6X6X7/8 Assign Material as: A709_50W | |||||
15 | Create a new section by defining its name as RigidSection | |||||
16 | Copy and pastethe data below.
|
...
1 | From any cell of the HammerHeadSec row, click on three-dots icon to open Section Editor panel. | ||||||
2 | Click + icon at the left top side of the screen. And Select Rebar | ||||||
3 | Enter:
Click Add. | ||||||
4 | Click … icon shown on top middle edge of rebar. Click Points Spreadsheet. Copy the data below.
| ||||||
5 | Paste copied data. | ||||||
6 | Click again + icon at the left top side of the screen. | ||||||
7 | again + icon at the left top side of the screen. | ||||||
5 | The reinforcement identification process will be carried out three times on the bottom reference edge. Select Rebar
Click Add. | ||||||
6 | |||||||
87 | Click … icon shown on top middle edge of rebar. Click Points Spreadsheet. Copy the data below.
| ||||||
98 | Paste copied data. | ||||||
109 | Click again + icon at the left top side of the screen. | ||||||
1110 | Select Rebar
Click Add. | ||||||
1211 | Click … icon shown on left middle edge of rebar. Click Points Spreadsheet. Copy the data below.
| ||||||
1312 | Paste copied data. | ||||||
1413 | Click again + icon at the left top side of the screen. | ||||||
1514 | Select Rebar
Click Add. | ||||||
1615 | Click … icon shown on right middle edge of rebar. Click Points Spreadsheet. Copy the data below.
| ||||||
1716 | Paste copied data. |
Info |
---|
Please follow the instructions provided below to set rebar detailing for HalfHammerHeadSec1. |
...