Follow the next steps to perform Punching Shear Code Check.
Table 1: Punching Shear
1 | Go to “Punching Shear” under 1st Floor from tree view. Click “Verify All” button. Check if all colums are "Passed". If there is a columns with "Failed" as in the figure click “Show” reports and investigate why code check verification failed. | |
2 | ||
3 | According to report It has been noticed that the Top Reinforcement area is insufficient, so it is necessary to increase the reinforcement area. Go to Flexural Reinforcement Tab at same spreadsheet. Click “Increase Top Reinforcement” button and then BDS will add seen in the spreadsheet Top Reinforcement Rebars to reinforcement area | |
4 | ||
5 | Then Then go to again "Column Strip Reinforcements" under Top Reinforcements from tree view. The rows are red because the Provide intensity value is insufficient.
To do this, either increase the "Rebar" value or decrease the "Spacing" value. The "Require Count" value will increase when you make the spacing smaller. | |
6 | ||
7 | ||
8 | Go to “Puncing Shear” under 1st Floor from tree view. Click “Verify All” button and all “Status” has been “Passed”. |
The “Punching Shear” part is completed in this step.
✓ 1st Floor Slab analysis of this Project has been completed.