Please follow the instructions provided below to define construction of bridge components.
1 | Navigate to Loading > Construction > Superstructre > Girder Construction | |
2 | Click three-dots icon on Stage cell.
Select the Stage as “GirderErection” | |
3 | Click three-dots icon on “Girders” cell. Pick all Girders in the project and then click on "Done" to finalize the process. | |
4 | Click three-dots icon on “Diaphragm” cell. Additionally, pick all diaphragms in the project adn clicking on “Done” |
Follow the below steps to copy and paste all inputs from our data set.
1 | Navigate to Girder Construction under Superstructure Construction on the tree view. |
2 | Copy Girder Construction from model inputs and paste into OpenBrIM |
Girder Construction |
---|
Girder Construction |
GirderConst GirderErection [PIG1,PIG2,PIG3,PIG4,PIG5,PIG6,PIG7,PIG8,PIG9,PIG10,PIG12,PIG11,PIG13,PIG14,PIG15,PIG16,PIG17] [CB1,CB2,CB3,CB4,CB5,CB9,CB10,CB6,CB11,CB12,CB7,CB8,CB13,CB14,CB19,CB15,CB20,CB16,CB21,CB22,CB17,CB23,CB18,CB24,CB25,CB26,CB27,CB28] |
Girder Construction | |
---|---|
Girders (spreadsheet) | Diaphragms (spreadsheet) |
PIG1 PIG2 PIG3 PIG4 PIG5 PIG6 PIG7 PIG8 PIG9 PIG10 PIG12 PIG11 PIG13 PIG14 PIG15 PIG16 PIG17 | CB1 CB2 CB3 CB4 CB5 CB9 CB10 CB6 CB11 CB12 CB7 CB8 CB13 CB14 CB19 CB15 CB20 CB16 CB21 CB22 CB17 CB23 CB18 CB24 CB25 CB26 CB27 CB28 |
0 Comments