Girder erection is typically only necessary to consider the non-composite state of girders in a design process. As a result, in general industry practice, girders and cross frames are erected in a single stage. However, if the user needs to model a detailed girder erection process, they can utilize the features available under the 'Girder Erection (Partial)' section

Please follow the instructions provided below to define construction of bridge components.

1

Navigate to Loading > Construction > Superstructre > Deck Erection (Complete)

2

Click three-dots icon on GirderStage cell.

Select the construction stage as 'GirderStage'

3

Click three-dots icon on Bridge cell.

Set the Bridge as 'BRG1'


Follow the below steps to copy and paste all inputs from our data set.

1

Navigate to Girder Erection (Complete) under Superstructure on the tree view.

2

Copy Girder Construction from model inputs and paste into OpenBrIM


 Quick Tip: Copy inputs to OpenBrIM

Copy the desired data with the automatic copy button in the upper left corner.

Click on the first cell in and use the Ctrl+V shortcut to paste.

If icon won’t appear, collapse page tree menu by clicking on arrow or using shortcut “[”.

While pasting large data, it would be handy to turn of Auto-refresh .

Girder Erecetion (Complete)

Girder Construction

GCE1	GirderStage	BRG1