Please follow the instructions provided below to define construction of substructure bridge components.
1 | Navigate to Loading > Construction > Substructre > Pile. | |
2 | Click three-dots icon on Stage cell and click select. | |
3 | Select "SubstrConstStage" as stage. | |
4 | Click three-dots icon on Substructures Above cell and click pick. | |
5 | Select all of the Substructures Above (Foundation) that were previously defined from the 3D View. | Figure will be added |
6 | Then click Done. |
Follow the below steps to copy and paste all inputs from our data set.
1 | Go to Pile under Substructure on the tree view. |
2 | Copy Pile Construction from model inputs and paste into OpenBrIM. |
Pile |
---|
Pile Construction |
PC3 SubstrConstStage [RF1,RF2,F1] [] 1 |