Please follow the instructions provided below to add piles.
1 | Navigate to Substructure > Pile. | |
2 | Click three-dots icon on Substructure and select or pick footing. The number of piles that placed under the foundations defined in the previous steps are as follows, based on the project specifications: RF1: 9 pieces RF2: 9 pieces F1: 25 pieces | |
3 | Click three-dots icon on the Section Data and click edit. Enter the section data as follows for P1 (Pile).
| |
4 | Apply the section data set from the previous step to all piles in the project, as they are identical. | |
5 | You can import or select pile section. | |
6 | Enter pile Longitudinal and Transverse Offset from the footing origin. | |
7 | Switch to FEA tab. Click three-dots icon on Pile Properties and edit. | |
8 | Enter Offset from the bottom of the footing. | |
9 | Edit Tx/Ty/Tz/Rz properties. | |
10 | Navigate back and enter Pile Capacity/Top of Pile Moment Release/Generate FEM. |