Versions Compared

Key

  • This line was added.
  • This line was removed.
  • Formatting was changed.

...

Expand
titlePier Footing Code Check
Pier Footing Code Check [SIG]
1

(blue star) 🖱️ Click the three-dots icon on the Code Check Template cell, and then set PierFootCCT.

Image Removed

image-20250121-122604.pngImage Added

2

As a result of these operations, an issue will appear on the OpenBrIM screen. This does not necessarily mean that any operation was done incorrectly. The issue will be resolved when the shear reinforcement profile in longitudinal direction, shear reinforcement profile in transverse direction and shear reinforcement material are defined in the next step.

3

Insert excerpt
_Quick Tips
_Quick Tips
nameIssue
nopaneltrue

4

(blue star) 🖱️ Click the three-dots icon on theSelect Pier Footing cell, and then set Footing1.

Image Removed

image-20250121-122713.pngImage Added

5

(blue star) 🖱️ Enter the Distance in Longitudinal direction from centroid Code Check Location (Dist. in Long. Dir. from Cent.) as 10.

Image Removed

image-20250121-122729.pngImage Added

6

(blue star) 🖱️ Enter the Distance in Transverse direction from centroid Code Check Location (Dist. in Trans. Dir. from Cent.) as 20.

Image Removed

image-20250121-122759.pngImage Added

7

(blue star) 🖱️ Keep the Check for For as default.

Image Removed

image-20250121-122812.pngImage Added

8

You can edit the Flexural Reinforcement parameters of Pier Footing Code Check from Flexural Reinforcement tab.

(blue star) 🖱️ Click the three-dots icon on the Reinforcement Material cell, and then set A615_60.

Image Removed

image-20250121-122828.pngImage Added

9

(blue star) 🖱️ Click three-dots icon on the Longitudinal Direction Reinforcement cell and click Edit.

Image Removed

image-20250121-122840.pngImage Added

10

(blue star) 🖱️ Please set the following values sequentially:

1st row - Top or Bottom: Bottom Rebar Profile: ASTMA615No8 Spacing of Reinforcement: 10 Distance to Extreme Fiber: 4
2nd row - Top or Bottom: Top Rebar Profile: ASTMA615No8 Spacing of Reinforcement: 10 Distance to Extreme Fiber: 4

Image Removed

image-20250121-122903.pngImage Added

11

(blue star) 🖱️ Click three-dots icon on the Transverse Direction Reinforcement cell and click Edit.

Image Removed

image-20250121-122918.pngImage Added

12

(blue star) 🖱️ Please set the following values sequentially:

1st row - Top or Bottom: Bottom Rebar Profile: ASTMA615No8 Spacing of Reinforcement: 10 Distance to Extreme Fiber: 4
2nd row - Top or Bottom: Top Rebar Profile: ASTMA615No8 Spacing of Reinforcement: 10 Distance to Extreme Fiber: 4

Image Removed

image-20250121-122944.pngImage Added

13

You can edit the Shear Reinforcement parameters of Pier Footing Code Check from Shear Reinforcement tab.

(blue star) 🖱️ Click the three-dots icon on the Shear Reinforcement Profile in Longitudinal direction cell, and then set ASTMA615No5.

Image Removed

image-20250121-123013.pngImage Added

14

(blue star) 🖱️ Click the three-dots icon on the Shear Reinforcement Profile in Transverse direction cell, and then set ASTMA615No5.

Image Removed

image-20250121-123025.pngImage Added

15

(blue star) 🖱️ Click the three-dots icon on the Shear Reinforcement Material cell, and then set A615_60.

Image Removed

image-20250121-123037.pngImage Added

16

(blue star) 🖱️ Keep the Spacing in Longitudinal directionDirection, Spacing in Transverse directionDirection, No. of Legs in Longitudinal directionDirection, No. of Legs in Transverse direction Direction and Shear Reinforcement as default.

Image Removed

image-20250121-123050.pngImage Added

17

(blue star) 🖱️ Set name as PierFootCC.

Image Removed

image-20250121-123106.pngImage Added

18

Proceed to the next step to verify the model.

...

Tip

To view the entire procedure explained on this page, please watch the recorded Video below.

20231031185837Pier Footing CC.mp4