Please follow the instructions provided below to create Pile Capacity check

1

To check the capacity of the Piles in this section, select the appropriate Pile Cap for the corresponding pile.

If the goal is to assess the strength of all substructure elements supported by piles, six distinct pile capacities need to be defined.

2

Navigate to Substructure Code Checks > Pile Capacity Check

Image Added
3

Enter the Pile Capacity Code Check name as in the figure

4

Click three-dots icon on Template and assign “PileCapacityCCT” all code checks

Image Added

5

Click three-dots icon on Pile Cap and click pick.

Image Added

Image Added

6

In the 3D view, choose the substructure elements as "Pile Cap” as in the figure.

...

Insert excerpt
_ConfluenceInclusions
_ConfluenceInclusions
nameTo access
nopaneltrue

...

Insert excerpt
_ConfluenceInclusions
_ConfluenceInclusions
nameCopyPaste
nopaneltrue

1

Navigate to Pile Capacity Check under Substructure Code Checks on the tree view.

2

Copy General from model inputs and paste into OpenBrIM.

Tip

The Pile Capacity Check have been created.

...

Anchor
ModelInputs
ModelInputs

Insert excerpt
_ConfluenceInclusions
_ConfluenceInclusions
namePasteTip
nopaneltrue

Pile Capacity Check

General

Code Block
languagexml
PileCapacity1	PileCapacityCCT	Pier_1
PileCapacity2	PileCapacityCCT	Pier_2
PileCapacity3	PileCapacityCCT	Pier_3
PileCapacity4	PileCapacityCCT	Pier_4
PileCapacity5	PileCapacityCCT	EndBent1
PileCapacity6	PileCapacityCCT	EndBent2