1 | Navigate to Deck > Concrete Deck. | |
2 | Click on the "Girders" column. Click “pick” from the combobox. Select the girders graphically you want to create a deck. | |
3 | Click on the three-dot icon located on the first cell of the Cross-Section and click “Edit” | |
4 | Click on the three-dot icon located on the first cell of the “Cross Section Location” Then designate the locations for the “Cross-Sections” data. Associate a "Cross Section" with each "support line." This assignment will result in a specific deck cross-section being established between the two selected support lines. In cases where the "Cross Section" changes between two support lines, the "Variation w/Next Segment" parameter is employed to define the attributes of the transitions between the sections. | |
5 | ||
6 | Navigate back to General spreadsheet. | |
7 | Set Material type as Fc_5ksi. | |
8 | Click on the three-dot icon located on the first cell of the Deck Reinforcement Data and click “Edit” | |
910 | Enter the Deck Reinforcement Data as in the figure. After completing this step, the reinforcement process for the "Deck1" deck will be finished. |
...
Insert excerpt | ||||||||
---|---|---|---|---|---|---|---|---|
|
...
Insert excerpt | ||||||||
---|---|---|---|---|---|---|---|---|
|
1 | Navigate to Concrete Deck under Deck on the tree view. |
2 | Copy General and 3D Settings from model inputs and paste into OpenBrIM. |
...
Tip |
---|
The Concrete Deck that have been created are illustrated below. |
...
...
Insert excerpt | ||||||||
---|---|---|---|---|---|---|---|---|
|
Anchor | ||||
---|---|---|---|---|
|
Concrete Deck | |||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|
General | 3D Settings | ||||||||||
|
|
Section Data | |||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Cross-Sections | Girders | Deck Reinforcement Data | |||||||||||||||
|
|
|