1 | Navigate Bracing > Lateral Bracing | ||||||
2 | Click three-dots icon on Girder cell and set (Tub Girders) G1 that the lateral bracing will be placed inside. | ||||||
3 | Define the stations of the right and left points of the created Lateral Bracing. Enter the following data for LB1 row’s Left Web Station [ft]: 3 Right Web Station [ft]: 10 | ||||||
4 | Click three-dots icon on Section cell and click select. Set the section to AISCWT6X29 from the opened window. | ||||||
5 |
| ||||||
6 | Define Left and Right stations each lateral bracings to G1 and G2 girders according to project. | ||||||
7 | You can make adjustments to the "Gusset Plate" tabs if you wish. |
...