Follow the next steps to define construction of bridge components. |
1 | Go to Loading/Construction/Superstructure,click Deck.||||
2 | Deck pouring and hardening are the states of deck construction stage and should be specified here. | |||
3 | Go to Deck Casting tab. | |||
4 | Specify names of the deck construction stages in Name. | |||
5 | Select pouring stages in Pouring Stage (Weight Only) and hardening stages in Hardening Stage (Gains Stiffness). | |||
6 | Select the deck to be constructed in the corresponding stage. | |||
7 | Go to the Longitudinal tab and specify the stations of deck pouring in the longitudinal direction. | |||
8 | Go to the Transverse tab and specify the stations of deck pouring in the transverse direction. This example includes a complete casting sequence. Therefore, Keep the Transverse Const. Type as Complete (as default). | |||
9 | From Loading/Construction/Superstructure, click Girder Erection (Complete). | |||
102 | Select Stage and Bridge. | |||
113 | Proceed with Superstructure Attachment Construction. | |||
124 | Name the cell. | |||
135 | Select Stage. | 14Go to Superstructure Attachment Elements and click on Pick. | ||
15 | Pick the barrier objects from 3D view. Then, click done after selection completed. |
...
Insert excerpt | ||||||||
---|---|---|---|---|---|---|---|---|
|
1 | Go to Deck under Superstructure on the tree view. | ||||
2 | Copy Deck Casting, Longitudinal and Transverse from model inputs and paste into OpenBrIM. | ||||
3 | Go to Girder Erection (Complete) under Superstructure on the tree view. | ||||
42 | Copy Girder Construction from model inputs and paste into OpenBrIM. | 5 | Go to Superstructure Attachment Construction under Superstructure on the tree view. | 6 | Copy General from model inputs and paste into OpenBrIM. |
...
Insert excerpt | ||||||||
---|---|---|---|---|---|---|---|---|
|
...
Deck
...
Deck Casting
Code Block |
---|
DeckCasting1 Cast1PourStage Cast123GainStiffStage Deck1 0 0
DeckCasting2 Cast2PourStage Cast123GainStiffStage Deck1 0 0
DeckCasting3 Cast3PourStage Cast123GainStiffStage Deck1 0 0
DeckCasting4 Cast4PourStage Cast45GainStiffStage Deck1 0 0
DeckCasting5 Cast5PourStage Cast45GainStiffStage Deck1 0 0 |
Longitudinal
Code Block |
---|
DeckCasting1 0 111
DeckCasting2 211 319
DeckCasting3 419 530
DeckCasting4 111 211
DeckCasting5 319 419 |
Transverse
...
DeckCasting1 Complete N/A N/A N/A N/A
DeckCasting2 Complete N/A N/A N/A N/A
DeckCasting3 Complete N/A N/A N/A N/A
DeckCasting4 Complete N/A N/A N/A N/A
DeckCasting5 Complete N/A N/A N/A N/A
Girder Erection (Complete) | ||
---|---|---|
Girder Construction
|
Superstructure Attachment Construction
General