Go to Foundation in the tree view. Enter Elevation feet -5 feet.

Tip

Verifies Foundation elevation operation

2

Go to the Mat below Foundation and click the Mat.

Draw the Mat Edge between columns on Cad view.

Enter values in the figure for blank cell

Tip

Verifies Mat Edge operation

3
Expand
title3D view

4

Draw the Mat Piece for the Shear-Wall on Cad view.

Enter values in the figure for blank cell

Tip

Verifies Mat Piece operation

5
Expand
title3D view

6

Go to the Pile caps below Foundation and click the Template.
Click Import pile caps button. Check the boxes in the figure.
(40 Tonne P8-P9-P10-P11-P12) and click import.

Tip

Verifies Import pile caps Database

7
Tip
8
Tip
9
Tip
10
Tip
11
Tip
12
Tip

25. Go to the Pile caps spreadsheet and click the Template button. Click the Import pile caps button. Check the boxes in the screenshot. (40 Tonne P8-P9-P10-P11-P12) and click import.

...

Info

It gives the properties of the selected templates on the right side of Database.

...

It gives the properties of the selected templates on the right side of Database.

7

Enter the values in the table for the material and rebar values.
Check that the values that can be changed can change

Image Added

Tip

Verifies template values that can change.

8

Go to Pile Caps below Foundation, click Assign Pile Cap Template. Select the Circular column as the object, click enter.

Set to Pile Template to P8 [40] and Pile Embedment Soil value 60 inch

Image Added

Tip

Verifies Pile Cap Assign

9
Expand
title3D view
Image Added

10

Tip

11

Tip

12

Tip

13

Tip

...

...

Info

Enter the values in the table for the material and rebar values.

Go to Pile Caps spreadsheet, click Assign pile cap template. Select the Circular column as the object, click enter. Choose one of the templates you imported (P8 [40] )

...